Sample deliverable · Worked example

Schedule Health Check

North Valley Water Treatment Plant

Report: DEMO-SHC-001Revision: 03 · October 2026Prepared by: CPMORA Project Controls

Fictional project, transparent calculations. This example uses a 173-activity model to demonstrate our review approach. All activities, records and assumptions are invented.

For PDF, choose Print and then your browser’s PDF option. On iPhone, use Share → Print to access print options.

01 · Executive summary

Resolve the handover logic before accepting the forecast.

The submitted example overlooks electrical turnover as a prerequisite for commissioning. Restoring this interface moves model completion by 24 working days. Electrical/control readiness then becomes controlling, with the mechanical completion branch available earlier.

256 WDCorrected completion
from model origin
+20 WDMovement from
reference plan
2 highPriority findings
requiring attention
3 mediumSupporting findings
to resolve
Recommended management disposition

Return the example forecast for targeted revision. Confirm the turnover interface and the basis for electrical and procurement durations, then issue a reconciled schedule and narrative for review.

Decisions needed

  1. Confirm electrical handover as a commissioning prerequisite.
  2. Agree supported remaining durations and vendor dates.
  3. Assign corrective actions and review the recalculated forecast.

What this review demonstrates

Traceable observations, schedule consequences, responsible owners and evidence needed to close each finding. Priority reflects review urgency; it is not a contractual or financial impact rating.

02 · Forecast & critical path

A visible bridge from reference to corrected forecast.

Completion comparison in working daysReference completion at working day 236, submitted scenario at 232, corrected scenario at 256. All values are calculated from fictional inputs.075150225300Reference plan236Submitted scenario232Corrected scenario256
Working days from a common model origin (WD 0). These are relative model dates, not calendar dates or a measured project delay.

Two comparisons, two starting points: corrected completion is 20 working days later than the reference plan (WD 236 to WD 256), and 24 working days later than the submitted scenario (WD 232 to WD 256). These are alternative comparisons to the same corrected finish; do not add them together.

Calculated milestone finish · WD = working day from common origin
MilestoneReferenceSubmittedCorrectedChange vs reference
Equipment received
NV-220
WD 79WD 89WD 89+10 WD
Electrical turnover
NV-420
WD 188WD 208WD 208+20 WD
Commissioning ready
NV-430
WD 188WD 184WD 208+20 WD
Substantial completion
NV-510
WD 236WD 232WD 256+20 WD

The submitted scenario omits NV-420 → NV-430. The corrected scenario adds that link without changing any current duration. Differences between those two scenarios isolate the effect of the interface correction.

Controlling sequence · corrected model

Engineering & coordinationPermits & work planningEnabling works & mobilizationConstruction releaseFoundations & equipment basesConstruction releaseTreatment structures & enclosureInstrumentation & controlsElectrical turnoverCommissioning releaseIntegrated commissioningPerformance demonstrationHandover & closeoutCompletion milestone

Parallel mechanical branch: process piping and equipment connections are ready at WD 184, 24 working days before the controlling handover. Procurement NV-210 carries 90 working days of total float in this scenario; this is distinct from the float at the shared mechanical turnover gate.

Float is calculated against the model’s earliest finish, with no contractual finish constraint. Shared downstream activities have zero float. This simplified model does not replace a P6 longest-path review.

Work breakdown & parallel work fronts

173 activities across 16 work packages and coordination gates.

Each package contains ten distinct tasks. Cross-package handovers connect design, procurement, construction, commissioning and closeout. All 173 activities feed the completion milestone.

Work-package timelineCorrected early-start and early-finish spans for sixteen work packages, using working days from a common origin.075150225300D · Engineering & coordinationP · Permits & work planningQ · Equipment procurement preparationE · Enabling works & mobilizationF · Foundations & equipment basesS · Treatment structures & enclosureY · Yard utilities & tie-insR · Process piping & supportsL · Electrical distribution installationI · Instrumentation & controlsU · Pumping system installationH · Chemical treatment systemT · Filtration system installationV · Site restoration & permanent accessC · Integrated commissioningO · Handover & closeout
Corrected package spans in working days. Teal identifies packages whose final task has zero total float; gray indicates available float. The 13 coordination activities and milestones appear in the full input register.
WBSWork packageTasksCorrected startCorrected finish
DEngineering & coordination10WD 0WD 32
PPermits & work planning10WD 32WD 52
QEquipment procurement preparation10WD 32WD 52
EEnabling works & mobilization10WD 52WD 75
FFoundations & equipment bases10WD 78WD 109
STreatment structures & enclosure10WD 109WD 146
YYard utilities & tie-ins10WD 78WD 109
RProcess piping & supports10WD 146WD 174
LElectrical distribution installation10WD 78WD 114
IInstrumentation & controls10WD 146WD 173
UPumping system installation10WD 146WD 165
HChemical treatment system10WD 146WD 165
TFiltration system installation10WD 146WD 168
VSite restoration & permanent access10WD 146WD 171
CIntegrated commissioning10WD 208WD 228
OHandover & closeout10WD 236WD 256

03 · Detailed review findings

From observation to a verifiable corrective action.

High: resolve before accepting the example forecast. Medium: support the update with a documented basis and a clear narrative. Evidence references below identify fictional records described in Section 05.

HighF-01

Commissioning can start before electrical turnover

Activity: NV-420 → NV-430 · Evidence: M-01 · submitted dependency list

Observation
The submitted scenario links commissioning readiness only to equipment installation. Electrical turnover is a separate required handover in the example execution plan.
Consequence
Restoring the electrical predecessor moves readiness from WD 184 to WD 208 and completion from WD 232 to WD 256. The isolated logic correction adds 24 working days to this scenario.
Action
Confirm the physical handover criteria with construction and commissioning; add the agreed finish-to-start link and recalculate.
Close when
Accepted handover checklist; corrected logic; recalculated schedule and narrative.
MediumF-02

Equipment delivery depends on an unconfirmed allowance

Activity: NV-210 · Evidence: M-01 + A-01 · procurement assumption

Observation
The current model uses 30 working days for fabrication and delivery versus 20 in the reference plan. The sample assumption register contains no vendor commitment supporting the 30-day allowance.
Consequence
Equipment receipt moves from WD 79 to WD 89. The equipment branch has 90 working days of total float after the logic correction; a sufficiently longer delivery duration could become controlling. Float is scenario-specific, not permission to defer procurement.
Action
Obtain a dated vendor manufacturing and shipping commitment. Reconcile transit, receipt and inspection allowances before updating the forecast.
Close when
Vendor record tied to NV-210; revised allowance and sensitivity review.
HighF-03

Electrical testing duration needs a documented basis

Activity: NV-410 · Evidence: M-01 + A-02 · duration assumption

Observation
Electrical and control readiness verification increases from 15 to 35 working days. The model records the revised allowance, but the example input package does not include quantities, crew assumptions or a test sequence.
Consequence
The electrical/control readiness branch controls the corrected scenario. Its duration therefore directly affects commissioning readiness while it remains the longest branch.
Action
Validate quantities, production rates, test packages, staffing and access with the electrical lead. Retain the basis with the update.
Close when
Agreed remaining-work estimate and test sequence supporting the duration.
MediumF-04

Site-access allowance changed without a release plan

Activity: NV-320 · Evidence: M-01 + A-03 · access assumption

Observation
Access and pad work increase from 5 to 8 working days. The example assumes the work area can be released as shown, without a supporting staged-access plan.
Consequence
The current branch finishes at WD 117 and carries 53 working days of total float. This change does not move completion in the model, but the release assumption still needs validation.
Action
Confirm the access sequence, work fronts and remaining quantities; update durations and interfaces if the release plan differs.
Close when
Agreed work-area release plan and supported remaining duration.
MediumF-05

The forecast narrative needs a change reconciliation

Activity: NV-510 · completion milestone · Evidence: M-01 + N-01 · example narrative gap

Observation
The submitted scenario omits a required interface and therefore shows an artificially early commissioning handover. The example narrative does not reconcile the duration changes and the logic correction.
Consequence
Management would see -4 working days of movement in the submitted scenario, while the corrected model shows 20. The 24-day difference must be explained separately from the duration changes.
Action
Prepare a concise bridge from reference to submitted to corrected completion, identifying assumptions, supporting records and unresolved decisions.
Close when
Narrative reconciles the milestone table and lists open assumptions.

04 · Action register

Agree the owners, then check the revised forecast.

FindingResponsible leadReview gateRequired closeout evidence
F-01 · HighScheduler + commissioning leadBefore forecast acceptanceAccepted handover checklist; corrected logic; recalculated schedule and narrative.
F-02 · MediumProcurement leadBefore next schedule updateVendor record tied to NV-210; revised allowance and sensitivity review.
F-03 · HighElectrical leadBefore forecast acceptanceAgreed remaining-work estimate and test sequence supporting the duration.
F-04 · MediumConstruction leadBefore next schedule updateAgreed work-area release plan and supported remaining duration.
F-05 · MediumProject manager + schedulerWith revised review packageNarrative reconciles the milestone table and lists open assumptions.

Acceptance sequence: confirm inputs → agree corrections → recalculate → reconcile milestones and narrative → review with the project manager. An assigned action is closed only when its supporting evidence and revised model have been checked.

05 · Review basis & traceability

Separate the calculations from the assumptions.

Calculated in this example

  • Early starts and finishes using a forward pass.
  • Late starts and total float using a backward pass.
  • Milestone movement between three model scenarios.
  • Effect of restoring one missing predecessor.

Model assumptions

  • 173 linked activities: 160 package tasks plus 13 coordination activities and milestones; common origin WD 0.
  • One uniform working-day calendar; integer durations.
  • Finish-to-start links with zero lag.
  • No actual dates, resource limits, constraints or costs.
Fictional evidence register · no real client files were used
ReferenceExample recordPurpose / status
M-01173-activity input register belowReproducible duration and relationship inputs.
A-01Procurement allowance: NV-210, 30 WDVendor confirmation unresolved.
A-02Electrical testing allowance: NV-410, 35 WDQuantity and production basis unresolved.
A-03Access allowance: NV-320, 8 WDWork-area release sequence unresolved.
N-01Example update narrative gapMilestone change reconciliation required.
Model input register · all 173 activities

The predecessor list is the corrected/reference logic. Only the submitted scenario omits NV-420 as a predecessor of NV-430. Durations are remaining working days.

Download model inputs & results

173 activities

ActivityDescription / work packageReference durationCurrent durationPredecessorsCorrected startCorrected finishTotal float
D-01Confirm treatment capacity and operating criteria
Engineering & coordination
33Start at WD 0030
D-02Verify existing-utility information
Engineering & coordination
33D-01360
D-03Complete process flow diagrams
Engineering & coordination
44D-026100
D-04Complete hydraulic profile
Engineering & coordination
33D-0310130
D-05Coordinate equipment arrangement
Engineering & coordination
44D-0413170
D-06Complete civil and structural interfaces
Engineering & coordination
44D-0517210
D-07Coordinate electrical load list
Engineering & coordination
33D-0621240
D-08Complete instrument and control philosophy
Engineering & coordination
44D-0724280
D-09Hold interdisciplinary constructability review
Engineering & coordination
22D-0828300
D-10Issue coordinated construction package
Engineering & coordination
22D-0930320
P-01Prepare construction permit package
Permits & work planning
33D-1032350
P-02Review excavation and utility permit needs
Permits & work planning
22P-0135370
P-03Coordinate outage and tie-in windows
Permits & work planning
33P-0237400
P-04Develop temporary drainage plan
Permits & work planning
22P-0340420
P-05Develop traffic and access plan
Permits & work planning
22P-0442440
P-06Review lifting and delivery routes
Permits & work planning
22P-0544460
P-07Coordinate inspection hold points
Permits & work planning
22P-0646480
P-08Complete preconstruction coordination meeting
Permits & work planning
11P-0748490
P-09Confirm work authorizations in example plan
Permits & work planning
22P-0849510
P-10Release enabling work package
Permits & work planning
11P-0951520
Q-01Prepare main equipment requisition
Equipment procurement preparation
22D-10323490
Q-02Issue vendor technical requirements
Equipment procurement preparation
22Q-01343690
Q-03Review vendor arrangement drawings
Equipment procurement preparation
33Q-02363990
Q-04Resolve equipment nozzle interfaces
Equipment procurement preparation
22Q-03394190
Q-05Review power and control interfaces
Equipment procurement preparation
22Q-04414390
Q-06Review factory-test procedure
Equipment procurement preparation
22Q-05434590
Q-07Confirm spare-parts and tool list
Equipment procurement preparation
11Q-06454690
Q-08Review delivery and lifting requirements
Equipment procurement preparation
22Q-07464890
Q-09Close technical submittal comments
Equipment procurement preparation
33Q-08485190
Q-10Release procurement submittal for acceptance
Equipment procurement preparation
11Q-09515290
E-01Establish survey control points
Enabling works & mobilization
22P-1052540
E-02Mobilize field offices and welfare facilities
Enabling works & mobilization
22E-0154560
E-03Install temporary fencing and access gates
Enabling works & mobilization
22E-0256580
E-04Establish temporary power and water
Enabling works & mobilization
33E-0358610
E-05Install erosion and sediment controls
Enabling works & mobilization
22E-0461630
E-06Locate and mark existing utilities
Enabling works & mobilization
33E-0563660
E-07Perform trial potholes at crossings
Enabling works & mobilization
33E-0666690
E-08Set out treatment-plant work areas
Enabling works & mobilization
22E-0769710
E-09Establish construction haul route
Enabling works & mobilization
33E-0871740
E-10Inspect enabling works before area release
Enabling works & mobilization
11E-0974750
NV-100Accept main equipment submittal
Equipment procurement
55Q-10525790
NV-210Fabricate and deliver main equipment
Equipment procurement
2030NV-100578790
NV-220Receive and release main equipment
Equipment procurement
22NV-210878990
NV-300Release work area
Construction release
33E-1075780
F-01Set out foundation excavation limits
Foundations & equipment bases
22NV-30078800
F-02Excavate treatment-building footings
Foundations & equipment bases
55F-0180850
F-03Prepare and inspect bearing surfaces
Foundations & equipment bases
22F-0285870
F-04Place blinding concrete
Foundations & equipment bases
22F-0387890
F-05Fix footing reinforcement
Foundations & equipment bases
44F-0489930
F-06Install sleeves and embedded services
Foundations & equipment bases
33F-0593960
F-07Set anchor-bolt templates
Foundations & equipment bases
22F-0696980
F-08Complete pre-pour inspection
Foundations & equipment bases
11F-0798990
F-09Place footing and grade-beam concrete
Foundations & equipment bases
33F-08991020
F-10Cure concrete and verify foundation release
Foundations & equipment bases
77F-091021090
Y-01Set out yard pipe alignments
Yard utilities & tie-ins
22NV-300788089
Y-02Excavate raw-water pipe trenches
Yard utilities & tie-ins
44Y-01808489
Y-03Prepare trench bedding
Yard utilities & tie-ins
22Y-02848689
Y-04Install raw-water yard mains
Yard utilities & tie-ins
55Y-03869189
Y-05Install treated-water yard mains
Yard utilities & tie-ins
55Y-04919689
Y-06Install yard isolation valves
Yard utilities & tie-ins
33Y-05969989
Y-07Complete thrust restraint and anchors
Yard utilities & tie-ins
33Y-069910289
Y-08Hydrostatically test yard piping
Yard utilities & tie-ins
22Y-0710210489
Y-09Backfill and compact pipe trenches
Yard utilities & tie-ins
44Y-0810410889
Y-10Inspect yard utility connections
Yard utilities & tie-ins
11Y-0910810989
L-01Set out electrical duct-bank routes
Electrical distribution installation
22NV-300, D-10788020
L-02Excavate and inspect duct-bank trenches
Electrical distribution installation
44L-01808420
L-03Install electrical conduits and spacers
Electrical distribution installation
44L-02848820
L-04Place duct-bank concrete and backfill
Electrical distribution installation
44L-03889220
L-05Construct electrical equipment pads
Electrical distribution installation
55L-04929720
L-06Install grounding grid and test points
Electrical distribution installation
33L-059710020
L-07Set switchgear and distribution panels
Electrical distribution installation
33L-0610010320
L-08Install cable trays and supports
Electrical distribution installation
44L-0710310720
L-09Pull feeder and distribution cables
Electrical distribution installation
55L-0810711220
L-10Inspect electrical installation before wiring
Electrical distribution installation
22L-0911211420
NV-310Foundation acceptance
Construction release
00F-101091090
S-01Set wall and column reinforcement
Treatment structures & enclosure
55NV-3101091140
S-02Install wall forms and embeds
Treatment structures & enclosure
44S-011141180
S-03Inspect structural concrete preparation
Treatment structures & enclosure
11S-021181190
S-04Place treatment-structure walls
Treatment structures & enclosure
33S-031191220
S-05Cure walls and remove forms
Treatment structures & enclosure
77S-041221290
S-06Erect building structural frame
Treatment structures & enclosure
55S-051291340
S-07Install roof framing and deck
Treatment structures & enclosure
44S-061341380
S-08Install roof weatherproofing
Treatment structures & enclosure
33S-071381410
S-09Install exterior wall panels and doors
Treatment structures & enclosure
44S-081411450
S-10Inspect enclosure and release internal work
Treatment structures & enclosure
11S-091451460
V-01Remove temporary utility crossings
Site restoration & permanent access
22Y-10, S-1014614865
V-02Grade permanent access roads
Site restoration & permanent access
33V-0114815165
V-03Install subbase and compact road sections
Site restoration & permanent access
33V-0215115465
V-04Install curbs and drainage inlets
Site restoration & permanent access
33V-0315415765
V-05Place permanent access-road surfacing
Site restoration & permanent access
33V-0415716065
V-06Construct operating walkways
Site restoration & permanent access
33V-0516016365
V-07Install permanent fencing and gates
Site restoration & permanent access
22V-0616316565
V-08Install exterior identification and safety signs
Site restoration & permanent access
22V-0716516765
V-09Restore disturbed site areas
Site restoration & permanent access
33V-0816717065
V-10Inspect permanent operating access
Site restoration & permanent access
11V-0917017165
NV-320Complete access and equipment pads
Construction release
58NV-31010911753
R-01Verify process piping spool dimensions
Process piping & supports
22S-10, NV-32014614824
R-02Install equipment-area pipe supports
Process piping & supports
44R-0114815224
R-03Receive and inspect fabricated pipe spools
Process piping & supports
22R-0215215424
R-04Install process inlet headers
Process piping & supports
44R-0315415824
R-05Install process discharge headers
Process piping & supports
44R-0415816224
R-06Install bypass and drain piping
Process piping & supports
33R-0516216524
R-07Install process isolation valves
Process piping & supports
33R-0616516824
R-08Complete weld and joint inspections
Process piping & supports
22R-0716817024
R-09Pressure-test process piping sections
Process piping & supports
33R-0817017324
R-10Release piping for final equipment connections
Process piping & supports
11R-0917317424
U-01Inspect pump packages on receipt
Pumping system installation
11NV-220, S-10, NV-32014614733
U-02Verify pump baseplate elevations
Pumping system installation
22U-0114714933
U-03Set pump baseplates
Pumping system installation
22U-0214915133
U-04Grout pump baseplates
Pumping system installation
33U-0315115433
U-05Set pumps and driver assemblies
Pumping system installation
22U-0415415633
U-06Complete shaft alignment
Pumping system installation
22U-0515615833
U-07Install suction and discharge accessories
Pumping system installation
33U-0615816133
U-08Install pump lubrication and seals
Pumping system installation
22U-0716116333
U-09Verify rotation and mechanical clearances
Pumping system installation
11U-0816316433
U-10Accept pump mechanical installation
Pumping system installation
11U-0916416533
H-01Inspect chemical-feed skid shipment
Chemical treatment system
11S-10, NV-320, Q-1014614733
H-02Install chemical skid support bases
Chemical treatment system
22H-0114714933
H-03Set chemical-feed skids
Chemical treatment system
22H-0214915133
H-04Install chemical storage connections
Chemical treatment system
33H-0315115433
H-05Install dosing lines and isolation valves
Chemical treatment system
33H-0415415733
H-06Install containment and drainage connections
Chemical treatment system
22H-0515715933
H-07Install chemical safety fixtures
Chemical treatment system
22H-0615916133
H-08Inspect chemical pipe joints
Chemical treatment system
11H-0716116233
H-09Flush and leak-test dosing circuits
Chemical treatment system
22H-0816216433
H-10Accept chemical-system mechanical installation
Chemical treatment system
11H-0916416533
T-01Inspect filtration equipment shipment
Filtration system installation
11S-10, NV-320, Q-1014614730
T-02Set filter vessels and support frames
Filtration system installation
33T-0114715030
T-03Install filter inlet and outlet manifolds
Filtration system installation
33T-0215015330
T-04Install backwash piping
Filtration system installation
33T-0315315630
T-05Install backwash valves and actuators
Filtration system installation
22T-0415615830
T-06Install filter drain and air connections
Filtration system installation
22T-0515816030
T-07Complete internal filter inspections
Filtration system installation
22T-0616016230
T-08Install filtration media
Filtration system installation
33T-0716216530
T-09Flush filtration and backwash circuits
Filtration system installation
22T-0816516730
T-10Accept filtration mechanical installation
Filtration system installation
11T-0916716830
NV-400Complete MCC and field wiring
Electrical turnover
1212L-1011412620
I-01Verify instrument index and tag list
Instrumentation & controls
22S-10, NV-4001461480
I-02Install field instrument mounting brackets
Instrumentation & controls
22I-011481500
I-03Install pressure and flow instruments
Instrumentation & controls
33I-021501530
I-04Install level and water-quality instruments
Instrumentation & controls
33I-031531560
I-05Install instrument junction boxes
Instrumentation & controls
22I-041561580
I-06Pull instrument and control cables
Instrumentation & controls
44I-051581620
I-07Terminate instrument signal circuits
Instrumentation & controls
33I-061621650
I-08Install PLC and network hardware
Instrumentation & controls
33I-071651680
I-09Load example control configuration
Instrumentation & controls
22I-081681700
I-10Complete cabinet and point-to-point checks
Instrumentation & controls
33I-091701730
NV-410Verify electrical and control readiness
Electrical turnover
1535NV-400, I-101732080
NV-420Electrical turnover accepted
Electrical turnover
00NV-4102082080
NV-230Complete final equipment connections
Mechanical turnover
1010NV-220, R-10, U-10, H-10, T-10, Y-1017418424
NV-430Commissioning ready
Commissioning release
00NV-230, NV-4202082080
C-01Approve example commissioning check sheets
Integrated commissioning
11NV-4302082090
C-02Verify water and utility availability
Integrated commissioning
11C-012092100
C-03Complete cold functional checks
Integrated commissioning
22C-022102120
C-04Verify motor start and stop commands
Integrated commissioning
22C-032122140
C-05Test process alarm functions
Integrated commissioning
22C-042142160
C-06Test permissives and safety interlocks
Integrated commissioning
22C-052162180
C-07Run automatic control sequences
Integrated commissioning
33C-062182210
C-08Perform wet process startup
Integrated commissioning
33C-072212240
C-09Balance process flows and chemical dosing
Integrated commissioning
33C-082242270
C-10Release plant for performance demonstration
Integrated commissioning
11C-092272280
NV-440Demonstrate plant performance
Performance demonstration
88C-102282360
O-01Compile signed commissioning records
Handover & closeout
22NV-440, V-102362380
O-02Prepare operating and maintenance manuals
Handover & closeout
33O-012382410
O-03Verify spare-parts turnover inventory
Handover & closeout
11O-022412420
O-04Prepare redline record drawings
Handover & closeout
33O-032422450
O-05Conduct operator classroom training
Handover & closeout
22O-042452470
O-06Conduct operator field training
Handover & closeout
22O-052472490
O-07Complete joint pre-handover walkdown
Handover & closeout
11O-062492500
O-08Close example critical punch-list items
Handover & closeout
33O-072502530
O-09Submit final handover record package
Handover & closeout
22O-082532550
O-10Confirm handover package acceptance
Handover & closeout
11O-092552560
NV-510Substantial completion
Completion milestone
00O-102562560

Inputs requested for a real engagement

Current native schedule and data date; applicable baseline and contract milestones; calendars and schedule settings; update narrative; procurement commitments; progress evidence; approved changes; and clarification of conflicting records. The review scope, file size, deliverables and turnaround are agreed before work starts.

06 · Interpretation & next steps

A review package built for decisions.

This worked example demonstrates a findings report and action register. A real review would identify the files and versions actually examined, distinguish verified facts from assumptions, and retain the evidence behind each recommendation.

The 20-working-day movement is a result of this fictional model, not an estimate of real project delay or contractual entitlement. Calendar dates, cost exposure, resource feasibility and forensic responsibility have not been evaluated. The reference scenario is an illustrative plan, not an approved contractual baseline.

Discuss your Schedule Health Check