| D-01 | Confirm treatment capacity and operating criteria Engineering & coordination | 3 | 3 | Start at WD 0 | 0 | 3 | 0 |
|---|
| D-02 | Verify existing-utility information Engineering & coordination | 3 | 3 | D-01 | 3 | 6 | 0 |
|---|
| D-03 | Complete process flow diagrams Engineering & coordination | 4 | 4 | D-02 | 6 | 10 | 0 |
|---|
| D-04 | Complete hydraulic profile Engineering & coordination | 3 | 3 | D-03 | 10 | 13 | 0 |
|---|
| D-05 | Coordinate equipment arrangement Engineering & coordination | 4 | 4 | D-04 | 13 | 17 | 0 |
|---|
| D-06 | Complete civil and structural interfaces Engineering & coordination | 4 | 4 | D-05 | 17 | 21 | 0 |
|---|
| D-07 | Coordinate electrical load list Engineering & coordination | 3 | 3 | D-06 | 21 | 24 | 0 |
|---|
| D-08 | Complete instrument and control philosophy Engineering & coordination | 4 | 4 | D-07 | 24 | 28 | 0 |
|---|
| D-09 | Hold interdisciplinary constructability review Engineering & coordination | 2 | 2 | D-08 | 28 | 30 | 0 |
|---|
| D-10 | Issue coordinated construction package Engineering & coordination | 2 | 2 | D-09 | 30 | 32 | 0 |
|---|
| P-01 | Prepare construction permit package Permits & work planning | 3 | 3 | D-10 | 32 | 35 | 0 |
|---|
| P-02 | Review excavation and utility permit needs Permits & work planning | 2 | 2 | P-01 | 35 | 37 | 0 |
|---|
| P-03 | Coordinate outage and tie-in windows Permits & work planning | 3 | 3 | P-02 | 37 | 40 | 0 |
|---|
| P-04 | Develop temporary drainage plan Permits & work planning | 2 | 2 | P-03 | 40 | 42 | 0 |
|---|
| P-05 | Develop traffic and access plan Permits & work planning | 2 | 2 | P-04 | 42 | 44 | 0 |
|---|
| P-06 | Review lifting and delivery routes Permits & work planning | 2 | 2 | P-05 | 44 | 46 | 0 |
|---|
| P-07 | Coordinate inspection hold points Permits & work planning | 2 | 2 | P-06 | 46 | 48 | 0 |
|---|
| P-08 | Complete preconstruction coordination meeting Permits & work planning | 1 | 1 | P-07 | 48 | 49 | 0 |
|---|
| P-09 | Confirm work authorizations in example plan Permits & work planning | 2 | 2 | P-08 | 49 | 51 | 0 |
|---|
| P-10 | Release enabling work package Permits & work planning | 1 | 1 | P-09 | 51 | 52 | 0 |
|---|
| Q-01 | Prepare main equipment requisition Equipment procurement preparation | 2 | 2 | D-10 | 32 | 34 | 90 |
|---|
| Q-02 | Issue vendor technical requirements Equipment procurement preparation | 2 | 2 | Q-01 | 34 | 36 | 90 |
|---|
| Q-03 | Review vendor arrangement drawings Equipment procurement preparation | 3 | 3 | Q-02 | 36 | 39 | 90 |
|---|
| Q-04 | Resolve equipment nozzle interfaces Equipment procurement preparation | 2 | 2 | Q-03 | 39 | 41 | 90 |
|---|
| Q-05 | Review power and control interfaces Equipment procurement preparation | 2 | 2 | Q-04 | 41 | 43 | 90 |
|---|
| Q-06 | Review factory-test procedure Equipment procurement preparation | 2 | 2 | Q-05 | 43 | 45 | 90 |
|---|
| Q-07 | Confirm spare-parts and tool list Equipment procurement preparation | 1 | 1 | Q-06 | 45 | 46 | 90 |
|---|
| Q-08 | Review delivery and lifting requirements Equipment procurement preparation | 2 | 2 | Q-07 | 46 | 48 | 90 |
|---|
| Q-09 | Close technical submittal comments Equipment procurement preparation | 3 | 3 | Q-08 | 48 | 51 | 90 |
|---|
| Q-10 | Release procurement submittal for acceptance Equipment procurement preparation | 1 | 1 | Q-09 | 51 | 52 | 90 |
|---|
| E-01 | Establish survey control points Enabling works & mobilization | 2 | 2 | P-10 | 52 | 54 | 0 |
|---|
| E-02 | Mobilize field offices and welfare facilities Enabling works & mobilization | 2 | 2 | E-01 | 54 | 56 | 0 |
|---|
| E-03 | Install temporary fencing and access gates Enabling works & mobilization | 2 | 2 | E-02 | 56 | 58 | 0 |
|---|
| E-04 | Establish temporary power and water Enabling works & mobilization | 3 | 3 | E-03 | 58 | 61 | 0 |
|---|
| E-05 | Install erosion and sediment controls Enabling works & mobilization | 2 | 2 | E-04 | 61 | 63 | 0 |
|---|
| E-06 | Locate and mark existing utilities Enabling works & mobilization | 3 | 3 | E-05 | 63 | 66 | 0 |
|---|
| E-07 | Perform trial potholes at crossings Enabling works & mobilization | 3 | 3 | E-06 | 66 | 69 | 0 |
|---|
| E-08 | Set out treatment-plant work areas Enabling works & mobilization | 2 | 2 | E-07 | 69 | 71 | 0 |
|---|
| E-09 | Establish construction haul route Enabling works & mobilization | 3 | 3 | E-08 | 71 | 74 | 0 |
|---|
| E-10 | Inspect enabling works before area release Enabling works & mobilization | 1 | 1 | E-09 | 74 | 75 | 0 |
|---|
| NV-100 | Accept main equipment submittal Equipment procurement | 5 | 5 | Q-10 | 52 | 57 | 90 |
|---|
| NV-210 | Fabricate and deliver main equipment Equipment procurement | 20 | 30 | NV-100 | 57 | 87 | 90 |
|---|
| NV-220 | Receive and release main equipment Equipment procurement | 2 | 2 | NV-210 | 87 | 89 | 90 |
|---|
| NV-300 | Release work area Construction release | 3 | 3 | E-10 | 75 | 78 | 0 |
|---|
| F-01 | Set out foundation excavation limits Foundations & equipment bases | 2 | 2 | NV-300 | 78 | 80 | 0 |
|---|
| F-02 | Excavate treatment-building footings Foundations & equipment bases | 5 | 5 | F-01 | 80 | 85 | 0 |
|---|
| F-03 | Prepare and inspect bearing surfaces Foundations & equipment bases | 2 | 2 | F-02 | 85 | 87 | 0 |
|---|
| F-04 | Place blinding concrete Foundations & equipment bases | 2 | 2 | F-03 | 87 | 89 | 0 |
|---|
| F-05 | Fix footing reinforcement Foundations & equipment bases | 4 | 4 | F-04 | 89 | 93 | 0 |
|---|
| F-06 | Install sleeves and embedded services Foundations & equipment bases | 3 | 3 | F-05 | 93 | 96 | 0 |
|---|
| F-07 | Set anchor-bolt templates Foundations & equipment bases | 2 | 2 | F-06 | 96 | 98 | 0 |
|---|
| F-08 | Complete pre-pour inspection Foundations & equipment bases | 1 | 1 | F-07 | 98 | 99 | 0 |
|---|
| F-09 | Place footing and grade-beam concrete Foundations & equipment bases | 3 | 3 | F-08 | 99 | 102 | 0 |
|---|
| F-10 | Cure concrete and verify foundation release Foundations & equipment bases | 7 | 7 | F-09 | 102 | 109 | 0 |
|---|
| Y-01 | Set out yard pipe alignments Yard utilities & tie-ins | 2 | 2 | NV-300 | 78 | 80 | 89 |
|---|
| Y-02 | Excavate raw-water pipe trenches Yard utilities & tie-ins | 4 | 4 | Y-01 | 80 | 84 | 89 |
|---|
| Y-03 | Prepare trench bedding Yard utilities & tie-ins | 2 | 2 | Y-02 | 84 | 86 | 89 |
|---|
| Y-04 | Install raw-water yard mains Yard utilities & tie-ins | 5 | 5 | Y-03 | 86 | 91 | 89 |
|---|
| Y-05 | Install treated-water yard mains Yard utilities & tie-ins | 5 | 5 | Y-04 | 91 | 96 | 89 |
|---|
| Y-06 | Install yard isolation valves Yard utilities & tie-ins | 3 | 3 | Y-05 | 96 | 99 | 89 |
|---|
| Y-07 | Complete thrust restraint and anchors Yard utilities & tie-ins | 3 | 3 | Y-06 | 99 | 102 | 89 |
|---|
| Y-08 | Hydrostatically test yard piping Yard utilities & tie-ins | 2 | 2 | Y-07 | 102 | 104 | 89 |
|---|
| Y-09 | Backfill and compact pipe trenches Yard utilities & tie-ins | 4 | 4 | Y-08 | 104 | 108 | 89 |
|---|
| Y-10 | Inspect yard utility connections Yard utilities & tie-ins | 1 | 1 | Y-09 | 108 | 109 | 89 |
|---|
| L-01 | Set out electrical duct-bank routes Electrical distribution installation | 2 | 2 | NV-300, D-10 | 78 | 80 | 20 |
|---|
| L-02 | Excavate and inspect duct-bank trenches Electrical distribution installation | 4 | 4 | L-01 | 80 | 84 | 20 |
|---|
| L-03 | Install electrical conduits and spacers Electrical distribution installation | 4 | 4 | L-02 | 84 | 88 | 20 |
|---|
| L-04 | Place duct-bank concrete and backfill Electrical distribution installation | 4 | 4 | L-03 | 88 | 92 | 20 |
|---|
| L-05 | Construct electrical equipment pads Electrical distribution installation | 5 | 5 | L-04 | 92 | 97 | 20 |
|---|
| L-06 | Install grounding grid and test points Electrical distribution installation | 3 | 3 | L-05 | 97 | 100 | 20 |
|---|
| L-07 | Set switchgear and distribution panels Electrical distribution installation | 3 | 3 | L-06 | 100 | 103 | 20 |
|---|
| L-08 | Install cable trays and supports Electrical distribution installation | 4 | 4 | L-07 | 103 | 107 | 20 |
|---|
| L-09 | Pull feeder and distribution cables Electrical distribution installation | 5 | 5 | L-08 | 107 | 112 | 20 |
|---|
| L-10 | Inspect electrical installation before wiring Electrical distribution installation | 2 | 2 | L-09 | 112 | 114 | 20 |
|---|
| NV-310 | Foundation acceptance Construction release | 0 | 0 | F-10 | 109 | 109 | 0 |
|---|
| S-01 | Set wall and column reinforcement Treatment structures & enclosure | 5 | 5 | NV-310 | 109 | 114 | 0 |
|---|
| S-02 | Install wall forms and embeds Treatment structures & enclosure | 4 | 4 | S-01 | 114 | 118 | 0 |
|---|
| S-03 | Inspect structural concrete preparation Treatment structures & enclosure | 1 | 1 | S-02 | 118 | 119 | 0 |
|---|
| S-04 | Place treatment-structure walls Treatment structures & enclosure | 3 | 3 | S-03 | 119 | 122 | 0 |
|---|
| S-05 | Cure walls and remove forms Treatment structures & enclosure | 7 | 7 | S-04 | 122 | 129 | 0 |
|---|
| S-06 | Erect building structural frame Treatment structures & enclosure | 5 | 5 | S-05 | 129 | 134 | 0 |
|---|
| S-07 | Install roof framing and deck Treatment structures & enclosure | 4 | 4 | S-06 | 134 | 138 | 0 |
|---|
| S-08 | Install roof weatherproofing Treatment structures & enclosure | 3 | 3 | S-07 | 138 | 141 | 0 |
|---|
| S-09 | Install exterior wall panels and doors Treatment structures & enclosure | 4 | 4 | S-08 | 141 | 145 | 0 |
|---|
| S-10 | Inspect enclosure and release internal work Treatment structures & enclosure | 1 | 1 | S-09 | 145 | 146 | 0 |
|---|
| V-01 | Remove temporary utility crossings Site restoration & permanent access | 2 | 2 | Y-10, S-10 | 146 | 148 | 65 |
|---|
| V-02 | Grade permanent access roads Site restoration & permanent access | 3 | 3 | V-01 | 148 | 151 | 65 |
|---|
| V-03 | Install subbase and compact road sections Site restoration & permanent access | 3 | 3 | V-02 | 151 | 154 | 65 |
|---|
| V-04 | Install curbs and drainage inlets Site restoration & permanent access | 3 | 3 | V-03 | 154 | 157 | 65 |
|---|
| V-05 | Place permanent access-road surfacing Site restoration & permanent access | 3 | 3 | V-04 | 157 | 160 | 65 |
|---|
| V-06 | Construct operating walkways Site restoration & permanent access | 3 | 3 | V-05 | 160 | 163 | 65 |
|---|
| V-07 | Install permanent fencing and gates Site restoration & permanent access | 2 | 2 | V-06 | 163 | 165 | 65 |
|---|
| V-08 | Install exterior identification and safety signs Site restoration & permanent access | 2 | 2 | V-07 | 165 | 167 | 65 |
|---|
| V-09 | Restore disturbed site areas Site restoration & permanent access | 3 | 3 | V-08 | 167 | 170 | 65 |
|---|
| V-10 | Inspect permanent operating access Site restoration & permanent access | 1 | 1 | V-09 | 170 | 171 | 65 |
|---|
| NV-320 | Complete access and equipment pads Construction release | 5 | 8 | NV-310 | 109 | 117 | 53 |
|---|
| R-01 | Verify process piping spool dimensions Process piping & supports | 2 | 2 | S-10, NV-320 | 146 | 148 | 24 |
|---|
| R-02 | Install equipment-area pipe supports Process piping & supports | 4 | 4 | R-01 | 148 | 152 | 24 |
|---|
| R-03 | Receive and inspect fabricated pipe spools Process piping & supports | 2 | 2 | R-02 | 152 | 154 | 24 |
|---|
| R-04 | Install process inlet headers Process piping & supports | 4 | 4 | R-03 | 154 | 158 | 24 |
|---|
| R-05 | Install process discharge headers Process piping & supports | 4 | 4 | R-04 | 158 | 162 | 24 |
|---|
| R-06 | Install bypass and drain piping Process piping & supports | 3 | 3 | R-05 | 162 | 165 | 24 |
|---|
| R-07 | Install process isolation valves Process piping & supports | 3 | 3 | R-06 | 165 | 168 | 24 |
|---|
| R-08 | Complete weld and joint inspections Process piping & supports | 2 | 2 | R-07 | 168 | 170 | 24 |
|---|
| R-09 | Pressure-test process piping sections Process piping & supports | 3 | 3 | R-08 | 170 | 173 | 24 |
|---|
| R-10 | Release piping for final equipment connections Process piping & supports | 1 | 1 | R-09 | 173 | 174 | 24 |
|---|
| U-01 | Inspect pump packages on receipt Pumping system installation | 1 | 1 | NV-220, S-10, NV-320 | 146 | 147 | 33 |
|---|
| U-02 | Verify pump baseplate elevations Pumping system installation | 2 | 2 | U-01 | 147 | 149 | 33 |
|---|
| U-03 | Set pump baseplates Pumping system installation | 2 | 2 | U-02 | 149 | 151 | 33 |
|---|
| U-04 | Grout pump baseplates Pumping system installation | 3 | 3 | U-03 | 151 | 154 | 33 |
|---|
| U-05 | Set pumps and driver assemblies Pumping system installation | 2 | 2 | U-04 | 154 | 156 | 33 |
|---|
| U-06 | Complete shaft alignment Pumping system installation | 2 | 2 | U-05 | 156 | 158 | 33 |
|---|
| U-07 | Install suction and discharge accessories Pumping system installation | 3 | 3 | U-06 | 158 | 161 | 33 |
|---|
| U-08 | Install pump lubrication and seals Pumping system installation | 2 | 2 | U-07 | 161 | 163 | 33 |
|---|
| U-09 | Verify rotation and mechanical clearances Pumping system installation | 1 | 1 | U-08 | 163 | 164 | 33 |
|---|
| U-10 | Accept pump mechanical installation Pumping system installation | 1 | 1 | U-09 | 164 | 165 | 33 |
|---|
| H-01 | Inspect chemical-feed skid shipment Chemical treatment system | 1 | 1 | S-10, NV-320, Q-10 | 146 | 147 | 33 |
|---|
| H-02 | Install chemical skid support bases Chemical treatment system | 2 | 2 | H-01 | 147 | 149 | 33 |
|---|
| H-03 | Set chemical-feed skids Chemical treatment system | 2 | 2 | H-02 | 149 | 151 | 33 |
|---|
| H-04 | Install chemical storage connections Chemical treatment system | 3 | 3 | H-03 | 151 | 154 | 33 |
|---|
| H-05 | Install dosing lines and isolation valves Chemical treatment system | 3 | 3 | H-04 | 154 | 157 | 33 |
|---|
| H-06 | Install containment and drainage connections Chemical treatment system | 2 | 2 | H-05 | 157 | 159 | 33 |
|---|
| H-07 | Install chemical safety fixtures Chemical treatment system | 2 | 2 | H-06 | 159 | 161 | 33 |
|---|
| H-08 | Inspect chemical pipe joints Chemical treatment system | 1 | 1 | H-07 | 161 | 162 | 33 |
|---|
| H-09 | Flush and leak-test dosing circuits Chemical treatment system | 2 | 2 | H-08 | 162 | 164 | 33 |
|---|
| H-10 | Accept chemical-system mechanical installation Chemical treatment system | 1 | 1 | H-09 | 164 | 165 | 33 |
|---|
| T-01 | Inspect filtration equipment shipment Filtration system installation | 1 | 1 | S-10, NV-320, Q-10 | 146 | 147 | 30 |
|---|
| T-02 | Set filter vessels and support frames Filtration system installation | 3 | 3 | T-01 | 147 | 150 | 30 |
|---|
| T-03 | Install filter inlet and outlet manifolds Filtration system installation | 3 | 3 | T-02 | 150 | 153 | 30 |
|---|
| T-04 | Install backwash piping Filtration system installation | 3 | 3 | T-03 | 153 | 156 | 30 |
|---|
| T-05 | Install backwash valves and actuators Filtration system installation | 2 | 2 | T-04 | 156 | 158 | 30 |
|---|
| T-06 | Install filter drain and air connections Filtration system installation | 2 | 2 | T-05 | 158 | 160 | 30 |
|---|
| T-07 | Complete internal filter inspections Filtration system installation | 2 | 2 | T-06 | 160 | 162 | 30 |
|---|
| T-08 | Install filtration media Filtration system installation | 3 | 3 | T-07 | 162 | 165 | 30 |
|---|
| T-09 | Flush filtration and backwash circuits Filtration system installation | 2 | 2 | T-08 | 165 | 167 | 30 |
|---|
| T-10 | Accept filtration mechanical installation Filtration system installation | 1 | 1 | T-09 | 167 | 168 | 30 |
|---|
| NV-400 | Complete MCC and field wiring Electrical turnover | 12 | 12 | L-10 | 114 | 126 | 20 |
|---|
| I-01 | Verify instrument index and tag list Instrumentation & controls | 2 | 2 | S-10, NV-400 | 146 | 148 | 0 |
|---|
| I-02 | Install field instrument mounting brackets Instrumentation & controls | 2 | 2 | I-01 | 148 | 150 | 0 |
|---|
| I-03 | Install pressure and flow instruments Instrumentation & controls | 3 | 3 | I-02 | 150 | 153 | 0 |
|---|
| I-04 | Install level and water-quality instruments Instrumentation & controls | 3 | 3 | I-03 | 153 | 156 | 0 |
|---|
| I-05 | Install instrument junction boxes Instrumentation & controls | 2 | 2 | I-04 | 156 | 158 | 0 |
|---|
| I-06 | Pull instrument and control cables Instrumentation & controls | 4 | 4 | I-05 | 158 | 162 | 0 |
|---|
| I-07 | Terminate instrument signal circuits Instrumentation & controls | 3 | 3 | I-06 | 162 | 165 | 0 |
|---|
| I-08 | Install PLC and network hardware Instrumentation & controls | 3 | 3 | I-07 | 165 | 168 | 0 |
|---|
| I-09 | Load example control configuration Instrumentation & controls | 2 | 2 | I-08 | 168 | 170 | 0 |
|---|
| I-10 | Complete cabinet and point-to-point checks Instrumentation & controls | 3 | 3 | I-09 | 170 | 173 | 0 |
|---|
| NV-410 | Verify electrical and control readiness Electrical turnover | 15 | 35 | NV-400, I-10 | 173 | 208 | 0 |
|---|
| NV-420 | Electrical turnover accepted Electrical turnover | 0 | 0 | NV-410 | 208 | 208 | 0 |
|---|
| NV-230 | Complete final equipment connections Mechanical turnover | 10 | 10 | NV-220, R-10, U-10, H-10, T-10, Y-10 | 174 | 184 | 24 |
|---|
| NV-430 | Commissioning ready Commissioning release | 0 | 0 | NV-230, NV-420 | 208 | 208 | 0 |
|---|
| C-01 | Approve example commissioning check sheets Integrated commissioning | 1 | 1 | NV-430 | 208 | 209 | 0 |
|---|
| C-02 | Verify water and utility availability Integrated commissioning | 1 | 1 | C-01 | 209 | 210 | 0 |
|---|
| C-03 | Complete cold functional checks Integrated commissioning | 2 | 2 | C-02 | 210 | 212 | 0 |
|---|
| C-04 | Verify motor start and stop commands Integrated commissioning | 2 | 2 | C-03 | 212 | 214 | 0 |
|---|
| C-05 | Test process alarm functions Integrated commissioning | 2 | 2 | C-04 | 214 | 216 | 0 |
|---|
| C-06 | Test permissives and safety interlocks Integrated commissioning | 2 | 2 | C-05 | 216 | 218 | 0 |
|---|
| C-07 | Run automatic control sequences Integrated commissioning | 3 | 3 | C-06 | 218 | 221 | 0 |
|---|
| C-08 | Perform wet process startup Integrated commissioning | 3 | 3 | C-07 | 221 | 224 | 0 |
|---|
| C-09 | Balance process flows and chemical dosing Integrated commissioning | 3 | 3 | C-08 | 224 | 227 | 0 |
|---|
| C-10 | Release plant for performance demonstration Integrated commissioning | 1 | 1 | C-09 | 227 | 228 | 0 |
|---|
| NV-440 | Demonstrate plant performance Performance demonstration | 8 | 8 | C-10 | 228 | 236 | 0 |
|---|
| O-01 | Compile signed commissioning records Handover & closeout | 2 | 2 | NV-440, V-10 | 236 | 238 | 0 |
|---|
| O-02 | Prepare operating and maintenance manuals Handover & closeout | 3 | 3 | O-01 | 238 | 241 | 0 |
|---|
| O-03 | Verify spare-parts turnover inventory Handover & closeout | 1 | 1 | O-02 | 241 | 242 | 0 |
|---|
| O-04 | Prepare redline record drawings Handover & closeout | 3 | 3 | O-03 | 242 | 245 | 0 |
|---|
| O-05 | Conduct operator classroom training Handover & closeout | 2 | 2 | O-04 | 245 | 247 | 0 |
|---|
| O-06 | Conduct operator field training Handover & closeout | 2 | 2 | O-05 | 247 | 249 | 0 |
|---|
| O-07 | Complete joint pre-handover walkdown Handover & closeout | 1 | 1 | O-06 | 249 | 250 | 0 |
|---|
| O-08 | Close example critical punch-list items Handover & closeout | 3 | 3 | O-07 | 250 | 253 | 0 |
|---|
| O-09 | Submit final handover record package Handover & closeout | 2 | 2 | O-08 | 253 | 255 | 0 |
|---|
| O-10 | Confirm handover package acceptance Handover & closeout | 1 | 1 | O-09 | 255 | 256 | 0 |
|---|
| NV-510 | Substantial completion Completion milestone | 0 | 0 | O-10 | 256 | 256 | 0 |
|---|